Press release

The implementation site is the headquarters and the premises of Trimetrik Kft. at 3523/63, 3523/62 Csucskai u. 12. Here is the company's plant, which consists of 3 buildings, on the roof of which the solar system will be installed. The aim of the project is to reduce the use of fossil energy and to reduce the cost of electricity consumption to a large extent.

ID: GINOP-4.1.4-19-2020-01457

Parameters of the solar system:

– Fronius ECO 25 wifi inverter with 5 years warranty / 25kW inverter 2 pcs.
– jinko solar 330 W monocrystalline solar panel / 10 years manufacturer’s warranty, 80,7% performance guarantee at the end of 25 years, 210 pcs.
– DC-AC side surge protection, electrical installation materials 2pcs
– mounting structure: aluminium rails, clamps, stainless steel bracket for tent, plate for roof 210 pcs

Activities carried out under the project:

Installation of a total of 87.12 kWp of solar panels for renewable energy production.